General Description :
Execution of mechanical installation operations of equipment, supply of equipment and accessories and complementary, execution of piping of CCM unit, remaining activities of supplementary plans, supply of items, materials and equipment, execution of piping operations, installation of equipment, supply of materials and purchase and repair and installation of cranes And the remaining activities of the foundry unit
Objective: To set up a continuous casting section of Esfarayen Steel Plant
The main activities performed in the project include:
– Acid washing of piping lines and preparation for charging grease and oil in the lines
– Oil flushing in piping lines
– Performing various tests on piping lines such as:
PT, NDT, RT, MT
– Construction and installation of single and double supports and clamps
– Sandblasting and color of piping lines and house pump
– Construction and installation of air tank with a capacity of 150 cubic meters and a height of 34 meters and 2 concrete tanks of 400 cubic meters
– Preparation, installation and commissioning of four cooling towers
– Preparation and installation
Scale and Oil Removal
– Reinforcement, formwork and concreting of equipment foundations
– Installing 660 valves in different sizes
– Installation of equipment and machines provided by the Italian company Danieli and under the supervision of that company in the amount of 582 tons.
– Preparation, construction and installation of 7 cranes with different types in capacities of 3 tons and 5 tons
– Preparation and installation of various types of piping materials such as pipes, valves, filters, fittings, expansion joints and 17 pumps
– Preparation and installation of two Self Cleaner devices (self-cleaning filter) made in Spain
– Preparation and installation of five devices
Exhaust Fan 1100 CFM
– Construction and installation of a stainless steel tank device
– Installation of 3 Heat Exchanger devices
– Preparation and installation of two Dosing Package devices
– Preparation and installation of 16 Split Units 24000
Preparation and installation of 3 devices
Unit Heater Gas Fired 25000
– Execution of refractory mass related to machines and parts
– Facade brickwork related to buildings constructed in the amount of 1050 square meters
– Construction of house pump building and sand filter
– Excavation, reinforcement, formwork and concreting for executive operations
– Preparation and implementation of ceiling and wall sandwich panels with the relevant reputation and flushing in the amount of 1450 square meters
– Execution of composite roof in the amount of 200 square meters
– Preparation and implementation of polyethylene pipes with a pressure of 10 times in 4 and 2 inch sizes at a rate of 900 meters
– Cooperation with the employer in launching the project
Employer : | Esfarayen Industrial Complex Company |
Start Date : | 2019 |
Total Duration : | 2 Years |
Strategies:
Development of Technical Knowledge and Expertise
Providing Competitive Price
Development of Communication Network
Creating a Culture of Commitment and Organization
Contact Us :
Address : Number 7 – Hatami Alley – Motahari St. – Tehran
Tel : 0098-88459970 (7 Line)
Fax : 0098-88415919
P.B : 15875-6869
E-mail : info@fanandish.com
Fundamental Values:
Health and professional ethics
Growth and organizational development
Providing Quality Services
Happiness and Personnel’s Satisfaction
Engineering Service Provider :
Operation, Maintenance and Repairs Projects
Construction, Erection and Commissioning Projects
Civil Projects
EPC Projects